NIPSCO HomeBack to Table of ContentsPreviousNext

NORTHERN INDIANA PUBLIC SERVICE COMPANY
IURC Electric Service Tariff
Original Volume No. 10
First Revised Sheet No. 18
Superseding
Original Sheet No. 18

RATE 844
RATE FOR ELECTRIC SERVICE
RAILROAD POWER SERVICE

No. 1 of 2 Sheets

TO WHOM AVAILABLE

This rate is available only to railroads receiving service from the Company on March 26, 1974 or to Public Agencies operating said railroads. Electricity will be supplied hereunder for the operation of trains on a continuous electrified right-of-way of the Customer and the
associated requirements furnished through the eight existing substations which are in service on July 16, 1987; provided, however, that electricity will not be furnished hereunder for resale.

CHARACTER OF SERVICE

The points of delivery shall be limited to the following substations as of the effective date of this tariff; Hammond substations at Columbia and at Carroll St., Gary substation at Third and Madison, Wickliffe substation, Furnessville substation and Michigan City substations, East Port I, East Port II, and Meer Road. The energy supplied by the Company shall be alternating current and at such voltages as currently supplied by the Company to the Customer.

RATE

Rates charged for service rendered under this schedule are based upon the measurement of electric energy at the voltage supplied to the Customer.

The electric service and energy supplied hereunder shall be billed under a two-part rate consisting of a Demand Charge plus an Energy Charge. Subject to the adjustments herein provided, said rate is as follows:

Demand Charge

$14.52 per month per kilowatt for all kilowatts of Billing Demand.

Energy Charge

37.073 mills per kilowatt hour for energy used per month for the first 660 hours of the Billing Demand for the month.

34.821 mills per kilowatt hour for energy used per month in excess of 660 hours of the billing Demand for the month.

RATE ADJUSTMENT

The above rates are subject to a Purchased Power Cost Adjustment Tracking Factor, in accordance with the Order of the Indiana Utility Regulatory Commission approved December 17, 1976, in Cause No. 34614. The Purchased Power Cost Adjustment Tracking Factor stated in Appendix A - Sheet No. 58 is applicable hereto and is issued and effective at the dates shown on Appendix A.




Issued Date Issued By
Edmund A. Schroer
Chairman and President
Effective Date
December 30, 1987 Hammond, Indiana December 30, 1987

PreviousNext