NIPSCO HomeBack to Table of ContentsPreviousNext

NORTHERN INDIANA PUBLIC SERVICE COMPANY
IURC Electric Service Tariff
Original Volume No. 10
First Revised Sheet No. 18.3C
Superceding
Original Sheet No. 18.3C

RIDER 848.2
ECONOMIC DEVELOPMENT RIDER TO GENERAL SERVICE - LARGE USE,
OFF_PEAK AND INDUSTRIAL POWER SERVICE
RATE SCHEDULES 824, 826, 832 AND 833

No. 4 of 5 Sheets

QUALIFYING CRITERIA (continued)

  1. Economic and/or Environmental Distress
  2. Power Use Characteristics
    1. High-efficiency, end-use equipment and construction technologies.
    2. High load-factor operations
    3. "Off-peak" operating capability.

  3. Site Specific Discounts
    1. Brown field site development.
    2. Community designated development or redevelopment zone.
    3. Industrial park location where municipal utilities, zoning and streets already exist.
    4. Utilization of existing industrial sites.
    5. Proximity to existing Company facilities.
    6. Loading of existing Company facilities.



    Issued Date Issued By
    Daniel D. Gavito
    Vice President, Regulatory & Government Policy - Indiana
    Effective Date
    March 26, 2003 Merrillville, Indiana March 26, 2003

    PreviousNext